Microsoft Project v4.0 for DOS
To run Microsoft Project, you need:
* MS-DOS operating system version 2.0 or later
* 256K of memory
* 1 MB of hard disk space recommended
* One 3.5" low-density (720K) or 5.25" low-density (360K) disk drive
Optional:
* Microsoft Mouse or compatible pointing device
Supported networks:
* AST! PC Network
* IBM PC Network
* Microsoft Networks
* Novell Netware
* 3Com 3+ and EtherSeries
* Ungermann-Bass Net/One
If you're looking for a project management package that can do it all,
and one that's easy to learn and use -- you're looking at it! Microsoft
Project offers a complete range of project scheduling and reporting
features and gets you up and running fast.
A full range of features and a friendly interface make it easy to track
and communicate project information, and a computer based tutorial helps
get you started.
Microsoft Project offers flexible, custom reports capabilites, so you'll
have complete comtrol of your report format and content. And you can
take advantage of extensive plotter support, so you can produce
presentation-quality charts.
* Filtering - view specific project information, so you can make more
informed decisions
* Sorting - arrange project information for analysis and reporting
* Resource leveling - resolve resource conflicts automatically
* Resource views - adjust schedules and resource assignments by viewing
several screens simultaneously
* Resource calendars - see what resources are actually available
* Resource histograms - view resources at a glance, so you can make
assignment adjustments
* Gantt Chart - see how long tasks are scheduled to take
* Network (PERT) Chart - view relationships between tasks and resources
* Start-to-finish/finish-to-start - model activity relationships
accurately
* Relationships with lead/lag - adjust relationships to accomodate
special scheduling needs
* Linked projects - track resources across projects
* CPM scheduling - calculate project finish dates and identify critical
activities automatically
* Project calendar - assign days off to project schedules
* Primavera utility disk - transfer data directly to Primavera Project
Planner
===========================